Common mistakes when building a house in the Philippines — 135° stirrups, roof insulation, grounding, solar and termites
In one line
A host who has been building a house in Angeles for about nine months lists common mistakes in Philippine house building and the shortcuts contractors tend to take. He says he has no construction background and that this is his own opinion from research and experience.
💡 Key takeaways
[Codes to know]
• The National Structural Code of the Philippines and the American Concrete Institute (ACI) standard — he says your contractor should know both well. He had ACI compliance written into his plans.
[Structure and concrete]
• Stirrup ends around column and beam rebar are usually bent to 90°, but 135° is stronger. The other 5–6 builds in his subdivision were also at 90°, and he thinks they won't do it unless the owner asks.
• Compact the soil before pouring with a mechanical (gas-powered) compactor, not a manual one.
• Check that concrete spacers are used so rebar isn't exposed.
• His house uses 4-inch CHB (concrete hollow block) walls. The columns and beams carry the load, so the block walls aren't load-bearing, and even if the blocks look sloppy they get plastered and skim-coated.
• For the second-floor slab he recommends a single monolithic pour and a mechanical concrete vibrator. Pouring by bucket in stages over several days is weaker, he says.
• He used steel decking — no forms to strip, so it's faster and uses less concrete.
• His builder takes concrete from the trucks into test cylinders and sends them to an outside facility for compressive strength testing.
[Roof and insulation]
• Metal roofs are the most common. He considers 0.4 the minimum thickness and chose 0.5.
• Insulation is aluminium foil foam, not fiberglass. The minimum is 5 mm; he used 10 mm double-sided foil for about 10,000 pesos more.
[Plumbing and waterproofing]
• Supply lines are PPR (ends fused with a dedicated machine), drains are PVC. Torching the ends together isn't the recommended method, he says.
• Do a pressure test before the walls are closed up (about 40–50 PSI at his site).
• Waterproof shower room floors — tile is not waterproof, he says. The product on his house is "Bastic Power Mix" per the captions.
• Sinks, toilets and showers need venting so they drain properly.
• Instead of a water tank he uses a pressure bladder, with a filtration system before it to extend its life.
• Some contractors vent bathroom exhaust fans and kitchen range hoods into the ceiling space; he says always vent them outside.
[Electrical and solar]
• The Philippines uses 220V. His house has both 110V and 220V.
• Grounding is not common. If you just ask for a "three-prong system" it may not be grounded, so ask for a system grounded to the earth with a grounding rod. GFI outlets are also rare.
• His electric bill is about 8,000–10,000 pesos a month. For a roughly 330 sqm house he is getting a 12 kW solar system for about 325,000–400,000 pesos, and expects payback in about 3–4 years.
[Building sequence]
• Walls → roof → plumbing and electrical → tiles → wall finishing → windows is the logical order, he says. His own build went out of order because of roofer availability and other reasons.
[Termites]
• Treat the soil before building, and he installed a reticulation system — perforated pipe around the perimeter for pumping in termiticide. The product is Soil Guard (main chemical cypermethrin), and he plans to treat yearly.
• Even in a concrete house, wooden door frames, cabinets and furniture can be damaged.
[Furniture, windows, garage door]
• Custom furniture takes about 45–90 days, and shops can't store it long, so time it right. Check termite treatment too.
• PVC cabinets cost about 20% more, so he chose laminate cabinets on marine plywood.
• Get windows tinted when you order them — aftermarket film scratches easily, he says.
• If zebra blinds go inside the window frame, discuss it with the window vendor in advance.
• Choose the garage door before the design is final. His opening didn't fit the available sizes, so the beam and column are being extended by about 6 inches.
[Closing advice]
• Decide what is and isn't acceptable to you and pick your battles.
• Communication often doesn't reach the workers, so keep talking with your builder and foreman.
⏱ Chapters
00:00 Introduction
03:55 Structure and concrete
07:24 Slab pour and strength testing
10:12 Roof and insulation
11:56 Plumbing and waterproofing
17:24 Electrical and solar
22:14 Termite protection
28:14 Closing advice
💬 What viewers said (200 comments)
• Many with building experience added tips — foil insulation should not touch the roof sheets, pressure test at 1.5 times operating pressure for 24 hours, a damp-proof membrane under the ground slab, and more.
• Many shared that shoddy work happens without supervision, and there was talk of daily pay versus contract (pakyawan) labour.
• Many agreed with his point to focus on column and beam rebar rather than the hollow blocks.
A friend building a house here kept having to call out shoddy work and not following the plans. After they messed up the bathroom tiling, the project manager told him: "Sir, your house will never be finished — because you want everything done properly!"
Watch where your rebar comes from — there's a lot of substandard material. When it's bent you can see cracks if you look closely; those are weak points. They will cut corners if you're not looking, not really on purpose — they're doing what they were taught, and they'll fix it if you say something. The good workers are on big job sites, so you get what's left.
3,000 square feet is pretty big. I see you have a beautiful pool too. It's probably more than I can afford, but I do want to build when I move to the Dumaguete area.