Building a House in Angeles Part 30 — Worker Wages, NBI Clearance, Final Payment, and the Late Roof
In one line
An American building a house in Angeles shows progress on the roof framing, plumbing, waterproofing and cistern, then answers viewer questions on worker wages, site clearance paperwork and contract terms.
💡 Key takeaways
[Workers and wages]
• The host's estimate: unskilled laborers earn about 500 pesos a day, skilled workers about 600–900 pesos (Angeles). He doubts you can hire anyone for 200 pesos a day.
• Most workers are unskilled; the plumbers, welder and electrician are school-certified. Masons and others may learn on the job (OJT).
• In this subdivision everyone working on site needs an NBI clearance, which can take several weeks — one cause of delays.
• Safety shoes and gear are the builder's responsibility, so the host doesn't provide them (flip-flops on site are common).
[Contract]
• He has a contract with the builder, including a penalty clause for delays.
• His final payment is about 10–12%; if doing it again he'd consider holding back about 25% for the last payment.
• Pushing penalty clauses too hard can make the builder price that risk into the build, so he advises finding a middle ground.
• It's a flat-price contract, so delay costs fall on the builder, but the host keeps paying rent while he waits.
[On site]
• The host thinks not getting the roof on early cost time lost to rain and heat.
• Bathrooms (CR) get waterproofing on the floor and part of the walls, then tile. Shower bathrooms will be tiled up to the ceiling.
• Water lines are PPR pipe, thicker-walled than PVC and said to be good for hot water. A pressure test with water and air is planned (ideally done before concrete covers it, he says).
• The underground cistern goes: concrete mixed with waterproofing agent → extra waterproofing → tile → concrete slab with a manhole.
• Subdivision water pressure is good for now, so he'll feed the house through a filter directly and switch to the cistern if pressure drops as more houses are built.
• Instead of a concrete box, the LPG tanks will sit outside with a hole through the wall to the range.
• Many Philippine homes put the light switch outside; he wants his inside. He's also adding a 110V outlet.
[Managing the build]
• He has no construction background but visits the site almost daily and catches things that get missed.
• He only half agrees with "leave your Western thinking at the door" — don't just stay quiet; speak up professionally and compromise.
⏱ Chapters
00:00 Site intro and update
01:38 Second-floor roof framing
06:12 PPR plumbing and leak test
07:55 Cistern and water supply
11:43 Electrical and garage
13:59 Answering viewer questions
16:04 Site management and wages
22:40 Contract terms and wrap-up
💬 What viewers said (49 comments)
• Several asked why the roof still isn't on; the host agreed and blamed poor planning and procrastination.
• A viewer building in Panglao said the wage estimates match their area.
• Experienced builders advised sleeving pipes, using a membrane-type waterproofing instead of cement-based, and keeping spare tiles.
• Many backed the host, saying how he spends his money is his own choice.
You were spot on. We worked hard and should be able to live wherever we choose and spend what we decide. Keep going with your dream retirement home. We'll start our own build once I retire from the federal government next year.
We're building our house in Panglao, acting as our own contractor. Your laborer wage estimate is spot on for our area. Our roof was delayed too, but it made a big difference once installed.
It still makes no sense why your roof isn't on.